Gwanggyo New Town Model District to Break Ground Next Month
Construction of the Gwanggyo New Town model district (Phase 1), which will supply a total of 7,797 units, is set to begin next month, with housing sales scheduled for October next year.
According to Suwon City, the Gwanggyo New Town model district will require a total project cost of 82.6 billion won and a construction period of 36 months.
The model district will be developed across an area of 1,067,184 square meters spanning Eui-dong in Yeongtong-gu, Suwon, and Sanghyeon-dong in Yongin, with plans to supply a total of 7,797 units.
In the Suwon area of the model district, 4,049 units of multi-family housing and 137 single-family homes will be supplied, while in the Yongin area, 3,611 units of multi-family housing will be supplied.
The model district originally planned 7,189 units, but as approximately 45,000 pyeong was allocated for a subway depot site near Kyonggi University, the residential land area decreased slightly, resulting in an upward adjustment of floor area ratio and an increase of 608 units in the supply scale.
This resulted from a decrease in the residential land ratio from 23 percent to 22 percent across the entire Gwanggyo New Town project area as the subway depot site was secured, and the floor area ratio was raised to meet the total housing supply volume of 31,000 units.
The city completed design review in July, requested site development construction bidding from the Public Procurement Service in August, and plans to proceed with bidding for construction this month or early next month before commencing work.