Master Plan for Suanin Line Station Area Development Expected to Take 2-3 Years

Basic Design for Suwon Station Rear Station Area Development, Including KCC Site Utilization, Needed to Shape 'Outline'

The outline of the basic plan for station areas around the Suanin Line stations, including Gosaek Station and Omok Stream Station, is expected to proceed in tandem with development plans for the KCC site, a rear area of Suwon Station.

Since March 2005, the City of Suwon has been undertaking construction of the first phase of the Suanin Line Suwon section—the Suwon Station (underground) to Seohocheon Entrance section (1.84 km)—with total project costs of 107.2 billion won.

According to the Light Rail Transit Project Division, a comprehensive master plan for station area development around Suwon Station, including the KCC site, must be finalized before the outline of development plans for Gosaek Station and Omok Stream Station becomes clear.

The remaining 3.06 km section, which includes Gosaek Station and Omok Stream Station, has not yet completed implementation plan approval, including detailed design involving the relocation of the bus depot.

An official from the Light Rail Transit Project Division explained, “Even if the bus depot site issue is resolved, the design and implementation plan approval process alone will take approximately 2-3 years.”